APARTMENT BUILDING · ÁLVARO OBREGÓN CMDX
Álvaro Obregón CMDX apartment building case study
The project uses more than 200 DN25 and DN40 meters with Wasion’s complete solution, covering field metering, communications and system deployment.
Project description based on installation conditions and operating results supplied by the project team.

PROJECT BACKGROUND
Water consumption across apartment buildings
The project brings building water readings into one connected metering solution. DN25 and DN40 meters provide different measurement capacities within a deployment of more than 200 meters, supporting visibility across the selected building service points.
User water consumption exceeds one tonne per day, with some users consuming more than four tonnes daily. The meters are distributed across the building, including demanding basement installation environments, making reliable reading collection and control of individual service points central to the project.
METERING APPROACH
DN25 and DN40 in one portfolio
DN25 measurement points
DN25 meters form the smaller-diameter part of the deployment. Their allocation to individual service points or sub-metering locations will follow the site plan.
DN40 supply measurement
DN40 meters cover the larger-diameter part of the project portfolio. They can support larger supply points in the building metering design, subject to flow requirements and installation conditions.
BUILDING METERING SOLUTION
Distributed meters, connected operations
The project connects DN25 and DN40 meters distributed across the apartment building to Wasion’s metering platform. Fixed-network collection achieves 97% communication efficiency, with AMR completing the remaining readings. Valve control supports abnormal-use monitoring and user-commanded closure during extended absences.

WASION COMPLETE SOLUTION
Coordinated delivery from meters to system
- 01
Meter selection and deployment
Coordinate DN25 and DN40 meter selection with the site requirements, then organize installation, device identification and commissioning for the project’s more than 200 meters.
- 02
Communications deployment
Plan the collection network around building layouts, meter access and field signal conditions. Configure the communications equipment and confirm that meters can transmit readings through the selected collection path.
- 03
System deployment
Bring meter records and readings into Wasion’s metering platform and HES. Organize the device information by building and measurement point to support centralized collection and operational review.
- 04
Complete-chain commissioning
Check the connection between each meter, its communications path and the system record. Review reading availability, identifiers and timestamps before the agreed operational handover.
- 05
Training and support
Include installation and operational guidance in the delivery plan, together with support for routine reading review and device maintenance. Operational guidance includes review of abnormal use and valve-control commands.
IMPLEMENTATION PLAN
Survey, pilot and staged deployment
The initial execution plan starts with an inventory of building supply and sub-metering points, followed by installation and communication checks on representative locations. Deployment then proceeds by building or zone, with meter registration and reading validation at each stage.
The distributed deployment includes extreme basement installation conditions. Reported communication efficiency reaches 97%; AMR reading completes collection for the remaining meters.
CONNECTED OPERATIONS
One view of building meter readings
Wasion’s complete solution connects distributed meters to the metering system for reading review by building and service point. Communication efficiency reaches 97%, with AMR collection completing the remaining readings.
The valve-control solution monitors abnormal water use. When users are away for an extended period, they can issue a valve-closing command to help prevent accidental leakage and unintended water use.
Explore the HES
OPERATIONAL REVIEW
Measures to validate during commissioning
The deployment reports 97% communication efficiency despite distributed meter locations and extreme basement conditions. AMR completes reading collection for the remaining meters, while abnormal-use monitoring and user-commanded valve closure support day-to-day management and protection during extended absences.
Related products and solutions
Plan a building metering deployment
Contact our teamProject scope supplied by the project team: apartment buildings, DN25 and DN40 meters, more than 200 meters in total, and Wasion’s complete solution. Updated operating information: daily consumption above one tonne, some users above four tonnes, distributed basement installation, 97% communication efficiency, supplementary AMR reading and valve control.